The most recent cost breakdown on the Main Street/Legion Drive project comes out $64,000 less than planned–$150,000 where items came in below budget vs.$76,000 in added expenses.
The new change order for Airport Road, alas, is $183,000 more. City Manager Greg Kisela predicts work on that road will be finished before summer tourist season kicks off.